S-34.1, r. 3 - Regulation respecting petroleum exploration, production and storage licences, and the pipeline construction or use authorization

Full text
118. A person who wishes to obtain a pipeline construction or use authorization must submit the following documents and information to the Régie de l’énergie, for its ruling on the pipeline construction or use project:
(1)  a detailed description of the project and the context justifying it;
(2)  for a construction project, a pipeline construction technical program, signed and sealed by an engineer, concerning, in particular, the equipment, tools, assembly materials and the measurement, control and safety systems;
(3)  a topographic map at a scale of 1:10,000 showing the actual or anticipated installations, including all its elements, the real or proposed route of the pipeline, and compliance with the distances provided for in section 131;
(4)  the criteria used to determine the proposed route;
(5)  a description of the location and area of the temporary work areas;
(6)  the work schedule for the construction, use, maintenance and temporary or permanent shutdown of the pipeline, including, in particular, a detailed description of each activity planned;
(7)  a demonstration, signed and sealed by an engineer, that the design of the pipeline, including, in particular, the construction, use, maintenance and temporary or permanent shutdown work, complies with the standards provided for in section 132 and that it ensures the safety of persons and property, and environmental protection;
(8)  a broken down estimate of the construction, use, maintenance and temporary or permanent shutdown work, and the income anticipated for the use of the pipeline;
(9)  the list of the permits, licences and authorizations required to carry out the project;
(10)  the list of the exploration, production and storage licences in force in the territory covered by the pipeline project and, where applicable, the business relationship between their holders;
(11)  the partners, their respective interests and their technical and financial capacities to carry out the project;
(12)  a summary of the public consultations carried out prior to the submission of the project; and
(13)  a description of the mitigation measures anticipated to harmonize the use of the territory and minimize disruptions for the local communities and on the environment.
If required and based on the environments crossed by the pipeline route, the person who wishes to obtain an authorization may, for the purposes of subparagraph 3 of the first paragraph, submit a number of types of maps including a topographic map and a bathymetric map.
O.C. 1253-2018, s. 118.
In force: 2018-09-20
118. A person who wishes to obtain a pipeline construction or use authorization must submit the following documents and information to the Régie de l’énergie, for its ruling on the pipeline construction or use project:
(1)  a detailed description of the project and the context justifying it;
(2)  for a construction project, a pipeline construction technical program, signed and sealed by an engineer, concerning, in particular, the equipment, tools, assembly materials and the measurement, control and safety systems;
(3)  a topographic map at a scale of 1:10,000 showing the actual or anticipated installations, including all its elements, the real or proposed route of the pipeline, and compliance with the distances provided for in section 131;
(4)  the criteria used to determine the proposed route;
(5)  a description of the location and area of the temporary work areas;
(6)  the work schedule for the construction, use, maintenance and temporary or permanent shutdown of the pipeline, including, in particular, a detailed description of each activity planned;
(7)  a demonstration, signed and sealed by an engineer, that the design of the pipeline, including, in particular, the construction, use, maintenance and temporary or permanent shutdown work, complies with the standards provided for in section 132 and that it ensures the safety of persons and property, and environmental protection;
(8)  a broken down estimate of the construction, use, maintenance and temporary or permanent shutdown work, and the income anticipated for the use of the pipeline;
(9)  the list of the permits, licences and authorizations required to carry out the project;
(10)  the list of the exploration, production and storage licences in force in the territory covered by the pipeline project and, where applicable, the business relationship between their holders;
(11)  the partners, their respective interests and their technical and financial capacities to carry out the project;
(12)  a summary of the public consultations carried out prior to the submission of the project; and
(13)  a description of the mitigation measures anticipated to harmonize the use of the territory and minimize disruptions for the local communities and on the environment.
If required and based on the environments crossed by the pipeline route, the person who wishes to obtain an authorization may, for the purposes of subparagraph 3 of the first paragraph, submit a number of types of maps including a topographic map and a bathymetric map.
O.C. 1253-2018, s. 118.